Station 51

Station 51 – Silverdale

Address: 10955 Silverdale Way, Silverdale, WA 98383
Serving the Silverdale communities
Architect: Rice Fergus Miller
Contractor: Clark Construction of Bainbridge Island
Construction period: October 2023 – December 2024
Size: 19,770 sqft
Design: 4-Drive through Apparatus Bays, 11-Dorm facility

Project Status

as of March 5, 2024

Site:

  • Excavation has been contained to the perimeter of the building footprint to mitigate winter inclement weather and runoff concerns.
  • The site excavation will be expanded to prep for the North side parking and driveway in March.

Building:

  • The building foundation has been completed to include all interior concrete flat work.
  • The building is in the framing stage.  The North and South ends of the building will be framed first.
  • Steel supporting columns are being erected, then the steel girder truss that supports the apparatus bay roof will be installed via crane by mid-March.
  • The majority of the building’s shell should be framed in by April 1, 2024.

Construction Progress