Station 51

Station 51 – Silverdale

Address: 10955 Silverdale Way, Silverdale, WA 98383
Serving the Silverdale communities
Architect: Rice Fergus Miller
Contractor: Clark Construction of Bainbridge Island
Construction period: October 2023 – December 2024
Size: 19,770 sqft
Design: 4-Drive through Apparatus Bays, 11-Dorm facility

Project Status

as of July 23, 2024

Site:

  • The West side of the property has had the stormwater detention system installed.
  • The North parking lot has been installed with an initial lift of asphalt laid.
  • The back (West side) concrete apron for the apparatus bays has been poured.
  • The utility work (gas, electricity, water, sewer, fiber, etc. is being installed on the South side of the property.
  • Work on the South access is being accomplished once utility work is finished.
  • Work on the front (Silverdale Way side) stormwater detention system will begin in August.

Building:

  • The building exterior is nearing completion.
  • The roof membrane is complete.
  • All windows have been installed.
  • Most of the metal siding and masonry veneer base and masonry bay door wraps have been installed.
  • Mechanical, plumbing, and electrical rough-ins are complete.
  • The building is being sheet-rocked.