Project Status

as of September 28, 2023

Site:

  • The stormwater retention pond’s perimeter fencing has been installed.
  • Concrete sidewalks and curbs have been poured on the West side of the project that support the employee parking area in preparation for asphalt.
  • The grades have been established and prepped for asphalt.
  • The exterior concrete apron has been poured in front of the apparatus bays.
  • The emergency generator has been installed.

Building:

  • The exterior masonry base has been installed.
  • The composite wood siding has been installed in specified locations.
  • The metal siding is being installed.
  • The apparatus bay doors have been installed.
  • The interior painting is complete.
  • Casework and countertops are being installed.
  • The concrete floors have been polished is specified areas.
  • Restroom tile work and showers are being installed.